GDS Holdings (GDS) Q3 2026 earnings review

GDS fills data centers faster, but its profit barely grows

GDS, which builds and runs large data centers in China, filled its halls faster but earned little more from them. Revenue grew 10%, but cash operating profit rose only 3% as power and other running costs climbed. GDS kept its full-year plan, which by our math puts fourth-quarter cash operating profit 7% below last year.

At a glance
RevenueRMB3,180.1M +10.1% from a year ago
Cash operating profit, excluding one-offsRMB1,380.2M +2.8% from a year ago
Share of finished space in use81.2% 74.4% a year ago
Full-year revenue and profit outlookUnchanged spending plan cut to about RMB8.5 billion

โš–๏ธ Verdict: ๐Ÿ”ด Bearish

The story got worse because new bookings slowed while power costs took a bigger share of revenue. Chief executive William Huang called the bookings strong, yet customers signed for a third less space than in the second quarter. The good news: move-ins beat the company's own plan, which shows the plan was cautious, not that revenue now arrives sooner.

The question now is whether bookings paused or settled at a lower level. A pause still allows the one-gigawatt target for the year; a lower level leaves GDS building ahead of demand. The full-year bookings total, due with fourth-quarter results, will settle it.

๐Ÿ‚ Bull Case

๐ŸŸข new GROWTH

Customers Moved In Faster Than GDS Planned

GDS earns revenue once customers move servers into space they signed for. Three months ago, finance chief Dan Newman forecast 90 megawatts of power capacity moving in during the second half. By our math, that is about 23,200 square meters.

Customers moved into 18,721 square meters in the third quarter alone. That is about 60% above half his second-half figure, by our math. The share of finished space in use reached 81.2%, against 74.4% a year ago.

So the beat shows a cautious plan, not bookings turning into revenue sooner. The same forecast leaves only about 4,500 square meters for the fourth quarter, by our math.

What to watch: fourth-quarter move-ins. A figure well above 4,500 square meters would mean Newman set the second-half forecast low again.

๐ŸŸข strengthening GROWTH

Almost All Space Being Built Is Pre-Sold

GDS signs customers before it finishes a building. Its pre-commitment rate shows the share of space under construction that customers have already agreed to take.

  • Space under construction already committed: 91.3%, from 73.0% a year ago
  • Space under construction: 191,930 square meters, up 12.7% from June
  • Finished space in service: up 0.8% from June

So most of the space GDS is building already has a buyer. The risk now sits in finishing it on time, not in selling it. But the space earns little until handover, and finance chief Dan Newman has said move-ins then take about four more quarters.

What to watch: finished space in service in the year-end results. A clear rise would show the pre-sold buildings turning into rooms customers can fill.

๐ŸŸข persistent GROWTH

Positives this quarter didn't test

Three positives from earlier this year got no new figures in the third-quarter release. Each rests on numbers management gave on its last call, and GDS repeated none of them this time.

  • Reservations, rights customers hold to take more space later: 600 megawatts of power capacity by mid-year, with chief executive William Huang aiming for over one gigawatt; the year-end total will move it
  • New campuses in Inner Mongolia, Ningxia and Guangdong: about half of first-half bookings; a regional split of new bookings would move it
  • Profit booked but not yet billed: about RMB1.6 billion a year at mid-year, by finance chief Dan Newman's estimate; an updated backlog would move it

๐Ÿป Bear Case

๐Ÿ”ด๐Ÿ”ด strengthening MARGIN

Power Costs Rose Faster Than Revenue

Data centers use large amounts of electricity, and GDS pays the utility bills in its halls. It blamed the drop in gross margin on "a higher level of utility costs as a percentage of net revenue".

  • Running costs before depreciation: up 19.0% from a year ago
  • Those running costs as a share of revenue: 52.9%, up 3.9 percentage points
  • Gross margin: 19.7%, from 22.1%
  • Cash operating margin, or adjusted EBITDA margin: 43.4%, from 46.5%

Two things moved against GDS, by our math. Revenue per square meter in use fell about 4%, while running costs per square meter rose about 4%. Lower corporate spending won back only about one percentage point.

This matters because finance chief Dan Newman has said prices per square meter will keep falling, partly because new campuses sit in lower-priced regions. If power costs per square meter keep climbing too, profit from the space GDS has booked will arrive smaller than its bookings suggest.

What to watch: running costs as a share of revenue next quarter. A further rise would mean the weak fourth-quarter profit in the plan reflects costs, not caution.

๐Ÿ”ด๐Ÿ”ด strengthening GROWTH contradicts narrative

New Bookings Slowed From the First Half

Bookings are contracts for space customers will move into later. Chief executive William Huang said GDS "secured strong new bookings while continuing to deliver our backlog". The bull case treats the first half's 470 megawatts of power capacity as a new pace of AI demand.

The release gives no megawatt figure. Net floor space signed for came to 39,074 square meters, a third below the second quarter. At the second quarter's ratio of power to floor space, that is roughly 170 megawatts by our math. Halls for AI chips draw more power per square meter, so the true figure may be higher.

This matters because the one-gigawatt target for the year needs about 530 megawatts in the second half. On our estimate, the fourth quarter would need roughly 360 megawatts. Huang has said the three largest cloud companies signed the first-half deals, so a pause by one would show quickly.

What to watch: the full-year bookings total in megawatts, due with the fourth-quarter results. A total well short of one gigawatt would mean the first half's pace did not last.

๐Ÿ”ด persistent CASH

Construction Bills Widened the Cash Shortfall

GDS pays for new halls before customers move in, and it borrows to cover the gap. The bull case counts on selling finished halls to a China-listed property fund it sponsors, a C-REIT, and reusing the cash.

  • Spending on buildings and equipment: RMB2,299 million, up 62% from a year ago
  • Free cash flow: minus RMB1,762 million, from minus RMB685 million
  • Total debt: RMB47.3 billion, up RMB1.1 billion since June

Finance chief Dan Newman cited "a solid financial position and liquidity". But operating profit barely covered the interest bill, by our math, and the release named no new sale to the fund.

What to watch: news of an asset sale to that fund, which management had pointed to for late 2026. Without one, heavier fourth-quarter spending rests on new debt.

๐Ÿ”ด persistent DISCLOSURE

Risks this quarter didn't answer

Four standing concerns got no new figures in the third-quarter release, so each stays open until GDS publishes the number that tests it.

  • Customer concentration: the largest customer took 34.9% of second-quarter revenue; the next customer breakdown will move it
  • Delay between bookings and revenue: the next move-in forecast for 2027 will move it
  • Power quotas and other regulation: the release gave no update; any change to power allocations for new campuses would move it
  • Dilution from convertible bonds and preferred shares: the weighted share count rose 1.3% from a year ago; a conversion would move it

๐Ÿ‘“ Other Themes

new MACRO

Lower Interest Rates Trimmed the Interest Bill

GDS paid RMB369.2 million in net interest, 1.7% less than a year earlier. It credited "lower interest rates as well as higher interest income" on its cash. Total debt grew over the same twelve months, so the cheaper rates explain the saving.

new GOVERNANCE

GDS Corrected How It Counted Shareholder Votes

GDS said earlier announcements counted 48,718,352 depositary shares, set aside for staff share awards, when measuring outside shareholders' voting power. Those shares carried no votes at the time, so they "should be excluded in calculating the voting power", the company wrote. With every share counted once, outside holders now have about 66.1% of the votes.

๐Ÿ’ฒ Other KPIs

Operating expenses as a share of revenue (26Q3) 7.7%
โ‡„ reversing

Selling, administrative and research costs took 7.7% of revenue, down from 9.6% a year ago. The share edged up from 7.3% in the second quarter. Excluding share-based pay and depreciation, corporate costs fell about 10%, which GDS credited to "savings on corporate expenses".

Net income (26Q3) RMB28.5 million
โ‡˜ decelerating

Net income fell 96%, because last year's quarter included a gain from selling data centers to the property fund. Excluding that gain, income before tax and stakes in other companies rose to RMB26 million from RMB2 million, by our math. Dividends on preferred shares left ordinary shareholders with a RMB5.5 million loss.

Accounts receivable (26Q3) RMB3,148 million
โ‡— accelerating

Money customers owe GDS rose 27.6% since December, while quarterly revenue grew 8.8% over the same span. By our math, customers now take about 90 days to pay. At the end of 2025, they took about 77 days. Changes in receivables and other working items tied up RMB419 million of cash this quarter.

๐Ÿ”ฎ Guidance

FY26 Revenue RMB12,700โ€“13,000 million
๐Ÿ † unchanged from RMB12,700โ€“13,000 million
โ‡’ stable

Unchanged. The plan still has sales rising about 12% this year, including a one-off payment GDS booked in the first quarter. By our math, that leaves about 10% growth for the fourth quarter, close to this quarter's pace. The range is wide enough to allow anything from 5% to 15%. Last year, revenue landed at the middle of the range.

FY26 Adjusted EBITDA (cash operating profit) RMB5,900โ€“6,100 million
๐Ÿ † unchanged from RMB5,900โ€“6,100 million
โ‡˜ decelerating

Unchanged. The plan has cash operating profit up about 11% this year, helped by a first-quarter one-off. By our math, that puts fourth-quarter profit about 7% below a year earlier. That margin would come to about 39%, the lowest in five quarters. GDS kept the range although this quarter beat half the second-half total. Last year it finished above the top.

FY26 Capital spending about RMB8,500 million
๐Ÿ ‡ cut from about RMB10,000 million
โ‡— accelerating

Cut. GDS now plans to spend about RMB1.5 billion less on buildings and equipment this year, and gave no reason. By our math, the new plan still leaves about RMB4.2 billion for the fourth quarter. That is almost twice the third quarter's spending, so the heaviest bills still fall at year-end.

โ“ Key Questions

How many megawatts did GDS book this quarter?

The release reports bookings only in square meters, a third below the second quarter. The one-gigawatt target for the year needs about 530 megawatts in the second half, so the megawatt figure shows whether it holds.

Why did GDS cut its spending plan this year?

GDS lowered its spending plan by about RMB1.5 billion without a reason, while space under construction kept rising. Readers need to know whether it pays suppliers later or builds less, because building less would delay move-ins in 2027.

What will power cost per square meter next year?

Utility costs drove the drop in margins this quarter. If power costs per square meter keep rising while prices per square meter fall, the profit GDS has booked will arrive smaller than its backlog suggests.

When will GDS sell more data centers to its fund?

Management had pointed to a second asset sale into its China-listed property fund in late 2026. The release did not mention it, and that sale is how GDS planned to recycle cash into new buildings.

What is the plan for the 19.9% DayOne stake?

DayOne, the Singapore-based data center group in which GDS holds a minority stake, added RMB38.6 million to results this quarter. GDS once talked about listing DayOne, then sold part of its stake back to it instead.