CleanSpark (CLSK) Q4 2026 earnings review
CleanSpark funds its data center, but bitcoin mining loses money
Bitcoin miner CleanSpark funded its first AI data center, while its mining business lost money. Revenue fell 46% from a year ago. By our math, operations lost about $123 million excluding gains on its bitcoin and a one-off write-down. Finance chief Gary Vecchiarelli said the new borrowing fully funds the Sandersville, Georgia, campus.
| Revenue | $120.9M −46% from a year ago |
|---|---|
| Operating result excluding bitcoin gains and one-offs, by our math | −$122.7M −$65.6M a year ago |
| Total debt | $4.08B $821M a year ago |
| First Sandersville data hall | Unchanged November 2027 |
⚖️ Verdict: 🔴 Bearish
The story got worse because mining no longer covers its costs while CleanSpark builds. Interest on the new notes will add about $179 million a year, by our math. On the other side, Sandersville construction is on time. But the tenant's exclusive right to the Texas sites expired without a lease.
The question now is whether CleanSpark signs a second tenant before interest and mining losses shrink its bitcoin reserve. Either Texas or Georgia wins a lease on Sandersville-like terms, or one campus carries all the new debt. A signed Texas lease would settle it, and the reports before Sandersville opens in November 2027 will show whether one arrives.
🐂 Bull Case
Sandersville Data Center Is Funded and On Schedule
CleanSpark is turning its mining site at Sandersville, Georgia, into a data center for AI computing. A high investment-grade tenant has signed a 20-year, $6.6 billion triple-net lease there. Under that structure, the tenant also pays the building's taxes, insurance and upkeep. Finance chief Gary Vecchiarelli said the new financing "fully funds the project".
This quarter the developer cut the risk of a late or costly build. It agreed a "turnkey, lump sum development contract" with its general contractor, paid ahead for equipment with long delivery times and obtained all material permits. CleanSpark says construction is "on time and on track to meet first planned data hall in November 2027".
This matters because the tenant pays rent only once halls open, so any delay pushes back all of the income. A fixed-price contract also means CleanSpark carries less of any cost overrun.
What to watch: the first-hall date in each quarterly report until November 2027. If that date holds through the coming year, the main risk left at Sandersville is the cost of the debt rather than the building.
Power Portfolio Grows to 2.1 Gigawatts
A data center developer needs land with a large grid connection before it can offer a tenant anything. CleanSpark now controls up to 2.1 gigawatts, against more than 1.8 gigawatts last quarter.
In Washington, Georgia, CleanSpark already has 86 megawatts connected to the grid. Early results from a power-line study point to "up to 500 MW transmission capacity over next several years", the company said. It also bought 500 acres next door "to support future AI data center campus".
This matters because more powered land gives CleanSpark more sites to offer, but each megawatt earns rent only after a tenant signs.
What to watch: the final result of the Washington study. A confirmed larger connection would give the developer a second Georgia site to offer tenants.
Positives this quarter didn't test
Three positives in the standing case got no clear reading this quarter. Each needs a figure that the press release left out, so each stays open until the annual report or a later call fills the gap.
- Digital Asset Management, its program of derivative trades on its bitcoin: $30.6 million of proceeds for the year, but no figure net of the quarter's derivative losses
- Lease extensions: the Sandersville tenant can extend twice by five years; a rent figure for those terms would show the full value
- Wider land pipeline: no update on sites under study beyond the current portfolio; a new purchase or study result would move it
🐻 Bear Case
Bitcoin Mining No Longer Covers Its Costs
CleanSpark has described bitcoin mining as the business that pays for its move into data centers. That plan works only while mining earns more than it costs to run. By our math, it stopped doing so this quarter, as revenue fell 46% from a year ago.
- Direct mining costs before depreciation: 65.7% of revenue, up 22.3 percentage points
- Earnings before interest, tax and depreciation, without bitcoin value gains: −$0.4 million, against $97.0 million a year ago, by our math
- Bitcoin mined: about 1,708 in the quarter by our math, against 1,925 in the third quarter
- Asset write-down: $171.7 million, with no assets named
The reported $9.8 million profit hides this. CleanSpark booked it only because the bitcoin it holds gained $305.6 million in value during the quarter. Over the full year, the same line cost $281.6 million, so the gain can reverse with the price.
What to watch: the coins mined and the direct cost per coin in the annual report. By our math, each coin cost about $46,600 to produce this quarter before overheads. A higher figure would mean mining needs cash from the bitcoin reserve during the build.
Texas Tenant Exclusivity Expired Without a Lease
CleanSpark bought two Texas sites this fiscal year, Sealy and Brazoria, with up to 885 megawatts between them. Last quarter the Sandersville tenant held exclusive rights to negotiate for the whole Texas portfolio. Regulators did move forward: ERCOT, the state's grid operator, gave 585 megawatts a conditional grid status called Batch Zero baseload, and Brazoria won state environmental permits.
But the exclusivity period expired "during a period of temporary regulatory uncertainty", CleanSpark said, and no lease followed. The developer says its efforts to find tenants continue "with existing Sandersville tenant and others".
This matters because the Texas sites earn rent only after a tenant signs. The release gives no new date for a deal, so CleanSpark's plan for a second campus has no timetable.
What to watch: a signed lease on Sealy or Brazoria Phase 1, the two parts with baseload status. A lease on terms like Sandersville's would show that the lapse reflected regulatory timing rather than weaker tenant interest.
Debt Rose Fivefold as Equity Fell Nearly Two-Thirds
Finance chief Gary Vecchiarelli said CleanSpark's strategy rests on "disciplined capital stewardship". The Sandersville money came from $2.276 billion of senior secured notes due 2031, with no new shares. That answers last quarter's question of whether the build could find funding, but it moves the risk to the cost of carrying the debt.
- Total debt: $4.08 billion, against $821 million a year ago
- Shareholders' equity: $786 million, against $2.18 billion
- Debt to equity: 5.2 times, against 0.4 times a year ago
- Yearly interest on the new notes at 7.875%: about $179 million by our math
These figures cut against the stewardship claim. By our math, interest on the new notes alone equals about 54% of the lease's average yearly rent. The year's $987 million net loss and a $463 million share buyback also shrank equity, so a thinner base now carries more debt.
What to watch: CleanSpark's plan for June 2028, when holders of older convertible notes can ask for $650 million back. That date falls about seven months after the first hall opens, so a refinancing plan before then would show the debt load is manageable.
Risks this quarter didn't answer
Four standing risks got little or no new information in the press release. Each has a disclosure that would move it, and most should appear in the annual report or on later calls.
- Construction timing: CleanSpark says Sandersville is on time, but the first real test comes when the first hall opens in November 2027
- Single tenant: one unnamed tenant holds the only lease; a second, named tenant would spread the risk
- Import tariffs: US customs authorities have claimed tariffs of up to about $130 million on miners imported in 2024; the release gave no update
- Lawsuits: a certified shareholder class action and suits naming senior officers continue, with no update in the release
💲 Other KPIs
CleanSpark's bitcoin reserve gained value after three quarterly declines, reaching $1.13 billion. Higher bitcoin prices explain the gain, because by our math the coin count slipped about 3% from June. With $205 million of cash, the reserve makes up the $1.3 billion of liquidity the developer cites.
The share count fell 8.4% from a year ago, after CleanSpark bought back 30.6 million shares in the fiscal year. Since June, though, the count crept up 1.4%. Future rent and profit will spread across about 260 million shares.
Money paid in advance for new mining machines fell 82% from a year ago, to $19.9 million. The balance has dropped for two straight quarters from $137 million in March, so the bitcoin miner now commits far less cash to new mining equipment.
🔮 Guidance
Unchanged. CleanSpark still plans to open the first Sandersville data hall in November 2027, inside the fourth quarter of 2027 it named last quarter. The tenant pays rent as halls open, so this date sets when the contracted income begins. Permits, prepaid equipment and a fixed-price building contract now stand behind the date.
Raised. The developer now counts up to 2.1 gigawatts of power, land and data centers. That compares with more than 1.8 gigawatts last quarter and 1.3 a year ago. By our math, the portfolio has expanded about 62% in a year. The release does not say which sites account for the step up.
Unchanged. The lease still runs 20 years and carries $6.6 billion of rent. By our math, that averages $330 million a year. That average equals about twice the gross profit mining earned this quarter on an annual basis, against about 1.6 times last quarter, because mining profit kept falling.
❓ Key Questions
When will CleanSpark sign a Texas tenant?
The Sandersville tenant's exclusive rights over Sealy and Brazoria expired without a lease. The sites hold conditional Batch Zero status on 585 megawatts. A timetable and a rent per megawatt would show whether Texas is delayed or stalled.
How much interest will CleanSpark pay before rent starts?
By our math the new notes cost about $179 million a year. The quarter showed only $4.2 million of interest expense. Readers need the cash interest bill for the period before the first hall opens.
Which assets did the $171.7 million write-down hit?
The release records the charge but does not name the assets. If it covers the Sandersville miners that must leave the site, CleanSpark should say where that part of the fleet will run.
How many bitcoin did CleanSpark mine in the fourth quarter?
The release gives only the full-year total of 7,253 coins. By our math the quarter produced about 1,708. A quarterly figure and the cost per coin would show how fast mining income is falling.
How will CleanSpark repay $650 million of notes in 2028?
Holders of older convertible notes can ask for repayment in June 2028, months after the first hall opens. The release does not say whether bitcoin sales, new debt or rent would cover it.